Guide
The Kansas City owner’s pre-construction checklist
The most expensive construction problems start before anyone breaks ground. Work through these twenty items before you sign a contract.
Most owners only build a few times in their lives. The contractors, suppliers, and designers across the table do it every day. This checklist evens the odds. It isn’t a substitute for professional advice on your specific project, but it covers the decisions we see cause the most cost and schedule trouble in the Kansas City market.
Budget & money
- Build a total project budget, not just a construction number: land, design fees, permits, utilities, furniture, IT, moving, financing, and contingency.
- Carry a design contingency and a separate construction contingency, and decide who controls each.
- Get an independent estimate at schematic design, before the design is too far along to change cheaply.
- Confirm your lender's draw process and inspection requirements before construction starts.
- Decide how allowances will be handled and reconciled.
Site, zoning & permits
- Confirm zoning, setbacks, parking, and use requirements with the right city. Kansas City, Missouri, Kansas City, Kansas, and each Johnson County city run their own planning and permitting offices.
- Ask early whether your project needs a plan review, rezoning, variance, or special use permit, and build that time into the schedule.
- Order a survey and geotechnical report before design is finalized.
- Check utility capacity and service lead times for power, water, sewer, and gas.
- Identify any historic, floodplain, or environmental reviews that apply to the site.
Team & contracts
- Choose a delivery method (design-bid-build, CM at risk, or design-build) that fits your budget certainty and schedule.
- Prequalify contractors on safety, financial strength, current workload, and comparable projects.
- Issue bid packages with scope sheets so every bidder prices the same work.
- Level bids line by line before choosing the low number.
- Read the contract for retainage, change order pricing, schedule damages, warranties, and insurance.
Schedule & handover
- Build a master schedule that includes design, permitting, long-lead equipment, construction, and move-in.
- Identify long-lead items (electrical gear, rooftop units, elevators, storefront) and release them early.
- Plan owner-furnished items (IT, security, furniture, signage) so they don't delay occupancy.
- Define closeout requirements up front: O&M manuals, as-builts, training, attic stock, and warranties.
- Schedule an 11-month warranty walk before the first year of coverage runs out.